| Cycle time estimation | |||
|---|---|---|---|
| The assumed cycle time is based on empirical values with the same or similar material, comparable geometry and size of the assembly to be welded and similar production concepts. Operator-dependent times are estimated values. | |||
| Project information | |||
| Customer | SJP Ultrasonics Pvt. Ltd. / Advik | ||
| Evosys project no. | 20-01280-SJP Pump | ||
| Machine type | EVO 1600-One welding operation per cycle | ||
| Input data - Process | |||
| Rotation speed | 90 | [*/sec] | |
| Rotation speed | 15 | [rpm] | |
| Welding angle | 380 | [°] | |
| Welding time | 4,22 | [sec] | |
| Process steps and cycle time | |||
| Operator: load/unload assy, Start buttom | Operator | 8,00 | [sec] |
| Laser safety door - Close | Machine | 1,50 | [sec] |
| Welding time - one welding | Machine | 4,22 | [sec] |
| Process evaluation and display of results | Machine | 0,10 | [sec] |
| Laser safety door - Open | Machine | 1,50 | [sec] |
| Total cycle time per part | 15,32 | [sec] | |
| Output per year with an estimated cycle time of 15,3 sec per part | |||
| Production days per yr. | 250 | [d] | |
| Hours per shift | 7,5 | [h] | |
| No. of shifts per day | 3 | [1] | |
| Machine availability | 90% | [%] | |
| Pieces per year | 1.189.449 | [1/a] | |